Key Research Findings:
Priority Rules in Project Scheduling
Scheduling a Portfolio of Projects with Resource Constraints
When the projects in a portfolio vie for the same pool of resources, how do portfolio (and project) managers decide which activities in which projects get priority?
What are the implications of their choice of heuristic?
Findings: The best prioritization heuristic depends on:
Whether minimizing delay to individual projects or to the overall portfolio
Project/Portfolio characteristics:
Network density
Iteration/rework intensity
Resource loading profile
Amount of resource contention
Key Publications: P21, P23, P34, P36
A project or portfolio manager who uses the same heuristic in all situations will perform very poorly.